冷再生施工和机械租赁业务
筑路架桥,奉献社会;以人为本,不断创新

服务热线

18264104888

新闻中心

首页>>新闻中心冷再生机的马达与减速机结合安装步骤

冷再生机的马达与减速机结合安装步骤

来源:http://www.tclqgc.com/ 日期:2023-04-14 发布人:
以施工速度快,效率高,受天气影响小,性能稳定、应用广泛而倍受客户称赞的冷再生机,足迹已经遍布到各地。那你对此设备了解多少呢?下面冷再生机出租厂家就来讲讲--冷再生机的马达与减速机结合安装步骤。
The cold recycling machine, which is highly praised by customers for its fast construction speed, high efficiency, minimal weather impact, stable performance, and wide application, has a footprint spread throughout the country. How much do you know about this device? Below, the rental manufacturer of the cold regeneration machine will talk about the installation steps of the motor and reducer combination of the cold regeneration machine.
步骤:
Step:
1、将设备启动移已选好场地,将转子罩弹簧销轴取出,再将转子放置低点,切记不可悬置或有吃力现象,造成大臂油缸销轴取不出来,油管泄压易出危险。
1. Start the equipment and move it to the selected site. Take out the spring pin of the rotor cover, and then place the rotor at a low point. Remember not to suspend or exert force, which may cause the pin of the boom oil cylinder to not be removed and the oil pipe may be in danger of pressure relief.
2、拆卸油管和转子马达的保护罩壳。
2. Remove the protective cover of the oil pipe and rotor motor.
3、将马达到工作泵的6根油管在大臂连接处全部拆卸开,并用卫生纸和塑料带将接口全部封紧,预防进入灰尘及杂物,并取下连接钢管。
3. Disassemble all 6 oil pipes from the motor to the working pump at the connection point of the boom, and seal all interfaces tightly with toilet paper and plastic tape to prevent dust and debris from entering. Remove the connecting steel pipe.
4、卸掉马达上的螺栓,并取下马达,注意需要两个人必须轻拿轻放。
4. Remove the bolts from the motor and remove the motor, taking care that two people must handle it gently.
5、将转子罩壳所有的连接杆拆卸,取下销轴。
5. Remove all connecting rods of the rotor housing and remove the pin shaft.
6、将连接两个大臂与固定横杆上的螺栓拆卸掉,只留两边上面的4个。
6. Remove the bolts connecting the two large arms and the fixed crossbar, leaving only four on both sides.
7、拆掉横杆和车体连接的4个螺栓,上下面做好标记,方便安装。
7. Remove the four bolts connecting the crossbar and the vehicle body, and mark the upper and lower parts for easy installation.
8、用吊车挂转子一侧的大臂处,另一侧挂马达后侧的销轴,先提升尽大量向一侧移动,然后将两根钢丝绳均挂到出来的那一侧,拖外面。
8. Use a crane to hang the large arm on one side of the rotor and the pin shaft on the back of the motor on the other side. First, lift as much as possible and move it to one side. Then, hang both steel wire ropes onto the side where they come out and drag them outside.
冷再生机出租
9、卸掉滑靴,吊出转子罩。
9. Remove the sliding shoes and lift out the rotor cover.
10、卸掉大臂与横杆和转子的连接处的螺栓,吊出大臂,放置一边。
10. Remove the bolts at the connection between the boom and the crossbar and rotor, lift out the boom, and place it aside.
11、卸掉减速机固定螺丝,并用撬棍插入轴套压住,用吊车吊出减速机,放置一边,检查有无渗漏现象。
11. Remove the fixing screws of the reducer and insert a pry bar into the shaft sleeve to press it down. Use a crane to lift out the reducer and place it aside to check for any leakage.
12、放开减速机的两个油堵,放净废油。因两个油堵成90度角,在加注新油时,减速机平放的基础上必须让注油孔在高点,直到观察孔漏油为止,然后将油堵缠上生料带上紧,如油堵是无‘O’型圈的类型,需在生料带的外面涂抹密封胶,观察12小时后有无渗漏现象。
12. Release the two oil plugs of the gearbox and drain the waste oil. Since the two oil plugs form a 90 degree angle, when filling new oil, the oil filling hole must be kept at a high point on the basis of the reducer placed horizontally until the observation hole leaks oil, and then the oil plug is wrapped around the Thread seal tape and tightened. If the oil plug is of the type without an 'O' ring, it is necessary to apply sealant on the outside of the Thread seal tape and observe whether there is leakage after 12 hours.
13、将以上步骤反之,安装完毕。
13. Reverse the above steps to complete the installation.
在安装的过程中,大臂、马达、减速机的固定螺栓均需涂抹紧固胶,马达与减速机结合面涂抹密封胶。更多相关内容就来我们网站http://www.tclqgc.com咨询!
During the installation process, the fixing bolts of the boom, motor, and reducer need to be coated with fastening adhesive, and the joint surface between the motor and reducer needs to be coated with sealant. For more related content, come to our website http://www.tclqgc.com consulting service

阅读/ Recommended reading

WR530V路面冷再生机是我公司新推出的路面冷再生机,这款产品不同于450和450机型,是一款完全胜任水稳路基冷再生施工的经济型冷再生机,主要技术参数向600机型看齐,产品综合性...

WR2100L冷再生机转子双转速的应用 2024-04-21
沥青路面养护为什么要使用冷再生机? 2024-04-21
你不知道的压路机选型要点 2024-04-11
旧沥青路面冷再生机械如何进行施工? 2024-04-09

产品/ Recommended products