冷再生施工和机械租赁业务
筑路架桥,奉献社会;以人为本,不断创新

服务热线

18264104888

新闻中心

首页>>新闻中心冷再生机租赁之水泥改良土施工流程

冷再生机租赁之水泥改良土施工流程

来源:http://www.tclqgc.com/ 日期:2021-06-03 发布人:
一、适用范围
1、 Scope of application
冷再生机出租为保证路床厚度范围内的CBR值和压实度达到规范要求,全线路床上部36cm厚采用6%水泥土处理。针对低填浅挖路基,当路基填方高度或挖方深度≤155cm时,路床下部44cm厚换填4%的水泥土处理,路床上部36cm厚换填6%水泥土处理。
In order to ensure that the CBR value and compactness within the thickness range of the roadbed meet the specification requirements, the upper part of the roadbed 36cm thick is treated with 6% cement soil. For low filling and shallow excavation subgrade, when the filling height or excavation depth of subgrade is less than or equal to 155cm, 4% of cement soil is replaced with 44cm in the lower part of roadbed, and 6% of cement soil is replaced with 36cm in the upper part of roadbed.
二、作业准备
2、 Homework preparation
1、冷再生施工租赁场地准备
1. Cold recycling construction rental site preparation
冷再生机租赁
(1)直接填筑的路基基底,施工前一定通过审查签证;需要进行地基处理的基底一定完成各项处理,并满足地基处理的要求。
(1) The subgrade base directly filled must pass the examination and visa before construction; The foundation that needs to be treated must be treated and meet the requirements of foundation treatment.
(2)场地应该保证足够的平整度,满足设备、人员进场要求。
(2) The site should be smooth enough to meet the requirements of equipment and personnel.
(3)做好场地的临时排水和防雨措施。按照施工运量和施工机械的大荷载修筑施工便道。
(3) Temporary drainage and rainproof measures should be taken. According to the construction traffic volume and the heavy load of construction machinery, the construction access road is built.
冷再生机租赁施工
Rental Construction of cold recycling machine
2、技术准备
2. Technical preparation
做好相关人员的技术培训和技术交底工作,使参加施工的全体人员充分认识高速铁路路基填筑的关键技术、质量控制要点。
Do a good job in the technical training and technical disclosure of relevant personnel, so that all personnel participating in the construction can fully understand the key technology and quality control points of high-speed railway subgrade filling.
3、劳动力、机械设备配置
3. Allocation of labor, machinery and equipment
人员、机械设备应根据施工方案组合工期要求进行合理的配置。路堤填筑区为一个完整的作业区,每个作业区人员配置:施工队长1名,领工员2名,指挥卸土位置人员2名,测量及试验检测人员4~6人,其他机械工、普工20~30人。
Personnel, machinery and equipment should be reasonably allocated according to the requirements of the construction scheme. The embankment filling area is a complete operation area, and the personnel allocation in each operation area is as follows: 1 construction team leader, 2 foreman, 2 personnel commanding the unloading position, 4-6 measurement and test personnel, 20-30 other mechanical workers and general workers.
根据施工需要,每个作业面配备反铲挖掘机一台、宣化-140推土机一台、YZ-22振动压路机两台、天工-160平地机一台,徐工-230灰土拌和机,自卸运输车6辆,撒水车一台备用。当运距较远时,自卸车的数量可适当增加。
According to the construction needs, each working face is equipped with a backhoe excavator, a xuanhua-140 bulldozer, two yz-22 vibratory rollers, a tiangong-160 grader, a xcmg-230 lime soil mixer, 6 dump trucks, and a sprinkling truck for standby. When the transportation distance is long, the number of dump trucks can be increased appropriately.

阅读/ Recommended reading

乳化沥青厂拌冷再生技术是以高品质再生乳化沥青作为结合料,采用专用拌和机械、化特种施工工艺的冷再生成套技术,实现公路建设低碳排放与绿色养护的减排高新技术,拌合过程中不消耗燃...

冷再生及土壤稳定机介绍 2024-03-29
水泥撒布车操作要注意什么? 2024-03-22
冷再生基层工程质量检测、控制及注意事项 2024-03-20
公路路面养护冷再生知识汇总 2024-03-17

产品/ Recommended products