冷再生施工和机械租赁业务
筑路架桥,奉献社会;以人为本,不断创新

服务热线

18264104888

新闻中心

首页>>新闻中心强夯机设备施工过程中应有人专门负责监测工作

强夯机设备施工过程中应有人专门负责监测工作

来源:http://www.tclqgc.com/ 日期:2022-06-27 发布人:
(1)开夯前应检查夯锤重和落距,以确保单击能量符合设计要求。
(1) Before tamping, the weight and falling distance of the rammer shall be checked to ensure that the click energy meets the design requirements.
(2)每遍夯击前,应对夯点放线进行复核,夯完后检查夯坑位置,发现偏差及时纠正。
(2) Before each tamping, the setting out of tamping points shall be rechecked. After tamping, the position of tamping pit shall be checked, and any deviation found shall be corrected in time.
(3)按要求检查每个夯点的夯击次数和每次的夯沉量。
(3) Check the tamping times and tamping settlement of each tamping point as required.
(4)在夯击中,当发现地质条件与设计提供的数据不符时应及时会同有关部门研究处理。
(4) When the geological conditions are found to be inconsistent with the data provided by the design during compaction, it shall be timely studied and handled with relevant departments.
(5)施工中对方案制定的工作量或要求进行改变时,应报上级主管技术部门批准后方可施工。
(5) In case of any change to the workload or requirements formulated in the scheme during construction, it shall be reported to the superior competent technical department for approval before construction.
(6)强夯施工中应在现场及时对各项参数及施工情况进行详细记录。
(6) During dynamic compaction construction, various parameters and construction conditions shall be recorded in detail on site.
(7)强夯过程中夯坑周围不应有过大的隆起,如有异常及时报告监理工程师,会同设计、业主等部门再作处理办法。
(7) During dynamic compaction, there shall be no excessive uplift around the tamping pit. If there is any abnormality, it shall be reported to the supervising engineer in time, and the handling method shall be made together with the design department, the owner and other departments.
冷再生机租赁
(8)夯坑应当日施工,当日推平,以防下雨泡水。
(8) The tamping pit shall be constructed and leveled on the same day to prevent rain and water.
(9)竣工验收后的强夯场地应及时投入使用,不应久置。
(9) The dynamic compaction site after completion acceptance shall be put into use in time and shall not be left for a long time.
(10)强夯竣工面应防止重型车辆碾压。
(10) The finished surface of dynamic compaction shall be prevented from being rolled by heavy vehicles.
冷再生机租赁厂家认为该设备的强夯法不仅能提高地基土的强度,降低其压缩性,还能改善抗振动液化的能力和土的湿陷性,因此它不仅适用于处理碎石土、砂土、粉土、黏性土、杂填土和素填土地基,还常用于处理可液化砂土地基和湿陷性黄土地基。
The leasing manufacturer of the cold recycling machine believes that the dynamic compaction method of the equipment can not only improve the strength of the foundation soil, reduce its compressibility, but also improve the anti vibration liquefaction ability and eliminate the collapsibility of the soil. Therefore, it is not only applicable to the treatment of gravel soil, sandy soil, silty soil, cohesive soil, miscellaneous fill and plain fill foundation, but also often used to treat liquefiable sand soil foundation and collapsible loess foundation.
以上就是问题解答的相关内容了,希望能够帮助到大家,如对这一问题还存在任何疑问,都欢迎关注我们网站http://www.tclqgc.com并咨询我们的工作人员,将竭诚为您服务。
The above is the relevant content of the question answer. I hope it can help you. If you still have any questions about this problem, you are welcome to follow our website http://www.tclqgc.com And consult our staff, will serve you wholeheartedly.

阅读/ Recommended reading

WR530V路面冷再生机是我公司新推出的路面冷再生机,这款产品不同于450和450机型,是一款完全胜任水稳路基冷再生施工的经济型冷再生机,主要技术参数向600机型看齐,产品综合性...

WR2100L冷再生机转子双转速的应用 2024-04-21
沥青路面养护为什么要使用冷再生机? 2024-04-21
你不知道的压路机选型要点 2024-04-11
旧沥青路面冷再生机械如何进行施工? 2024-04-09

产品/ Recommended products